#1 Processing Facility — Inspections
Total: 11 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 03/03/2005 | 03/03/2005 | J & L Drilling, Inc | 3.00 | 1 |
| 11/04/2004 | 01/04/2005 | J & L Drilling, Inc | 5.00 | 1 |
| 09/02/2004 | 09/08/2004 | J & L Drilling, Inc | 22.00 | 1 |
| 11/17/2003 | 11/17/2003 | J & L Drilling, Inc | 2.00 | 1 |
| 09/17/2003 | 09/17/2003 | J & L Drilling, Inc | 2.00 | 1 |
| 07/31/2003 | 07/31/2003 | J & L Drilling, Inc | 2.00 | 1 |
| 02/06/2003 | 02/06/2003 | J & L Drilling, Inc | 3.00 | 1 |
| 09/09/2002 | 09/09/2002 | J & L Drilling, Inc | 2.00 | 1 |
| 03/27/2002 | 03/28/2002 | J & L Drilling, Inc | 4.50 | 1 |
| 03/14/2002 | 03/14/2002 | J & L Drilling, Inc | 2.00 | 1 |
| 02/11/2002 | 02/11/2002 | J & L Drilling, Inc | 3.00 | 1 |