| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 07/09/2009 | 07/09/2009 | Marshall Mining Inc | 9.00 | 2 |
| 06/01/2009 | 06/01/2009 | Marshall Mining Inc | 5.50 | 1 |
| 05/21/2009 | 05/21/2009 | Marshall Mining Inc | 4.00 | 1 |
| 04/08/2009 | 06/25/2009 | Marshall Mining Inc | 17.50 | 2 |
| 01/05/2009 | 03/24/2009 | Marshall Mining Inc | 219.25 | 3 |
| 11/13/2008 | 12/31/2008 | Marshall Mining Inc | 171.75 | 4 |
| 08/07/2008 | 09/04/2008 | Marshall Mining Inc | 44.50 | 3 |
| 06/09/2008 | 06/10/2008 | Marshall Mining Inc | 12.50 | 3 |
| 04/17/2008 | 05/21/2008 | Marshall Mining Inc | 24.00 | 2 |
| 10/01/2007 | 11/06/2007 | Ember Contracting Inc | 8.00 | 2 |
| 07/30/2007 | 09/27/2007 | Ember Contracting Inc | 98.50 | 2 |
| 04/04/2007 | 06/21/2007 | Ember Contracting Inc | 68.00 | 2 |
| 02/05/2007 | 03/01/2007 | Ember Contracting Inc | 79.50 | 1 |
| 10/04/2006 | 12/27/2006 | Ember Contracting Inc | 64.50 | 2 |
| 08/17/2006 | 08/31/2006 | Ember Contracting Inc | 66.00 | 1 |
| 07/10/2006 | 07/10/2006 | Ember Contracting Inc | 8.00 | 1 |
| 04/26/2006 | 05/15/2006 | Ember Contracting Inc | 48.00 | 2 |
| 01/19/2006 | 03/27/2006 | Ember Contracting Inc | 51.00 | 1 |
| 11/15/2005 | 11/15/2005 | Ember Contracting Inc | 5.50 | 1 |
| 10/03/2005 | 12/09/2005 | Ember Contracting Inc | 117.50 | 2 |
| 07/27/2005 | 09/21/2005 | Ember Contracting Inc | 73.00 | 2 |