Axton Wash Plant — Inspections

Total: 10 inspections

Begin End Operator Hours Inspectors
09/05/2012 09/05/2012 Granite Construction Company 9.00 1
02/16/2011 02/17/2011 Granite Construction Company 16.00 1
02/18/2010 02/18/2010 Granite Construction Company 10.50 1
03/09/2009 03/10/2009 Granite Northwest Inc 13.00 1
02/12/2009 02/12/2009 Granite Northwest Inc 5.00 1
01/16/2008 01/17/2008 Wilder Construction Company 16.00 1
04/24/2007 04/25/2007 Wilder Construction Company 12.50 1
02/01/2006 02/02/2006 Wilder Construction Company 13.00 1
09/22/2005 11/15/2005 Wilder Construction Company 26.00 1
09/15/2005 09/15/2005 Wilder Construction Company 14.00 1