Begin End Operator Hours Inspectors
12/16/2015 12/16/2015 Bartley & Bolin Inc 3.75 1
07/28/2015 07/29/2015 Bartley & Bolin Inc 16.75 1
02/04/2015 02/04/2015 Bartley & Bolin Inc 0.50 1
02/04/2015 02/04/2015 Bartley & Bolin Inc 6.25 1
08/25/2014 08/26/2014 Bartley & Bolin Inc 14.00 1
01/08/2014 01/08/2014 Bartley & Bolin Inc 11.00 1
06/19/2013 06/19/2013 Bartley & Bolin Inc 10.00 1
01/28/2013 01/28/2013 Bartley & Bolin Inc 8.50 1
06/27/2012 06/28/2012 Bartley & Bolin Inc 24.50 1
01/23/2012 01/23/2012 Bartley & Bolin Inc 5.00 1
01/18/2012 01/18/2012 Bartley & Bolin Inc 5.50 1
05/04/2011 05/05/2011 Bartley & Bolin Inc 2.50 1
01/20/2011 01/20/2011 Bartley & Bolin Inc 13.25 1
08/10/2010 08/10/2010 Bartley & Bolin Inc 8.50 1
09/24/2008 09/24/2008 Lakeville Sand & Gravel 3.00 1
11/05/2007 11/06/2007 Lakeville Sand & Gravel 9.50 1
10/30/2006 10/30/2006 Lakeville Sand & Gravel 10.00 1
11/01/2005 11/02/2005 Lakeville Sand & Gravel 12.50 1
11/09/2004 11/09/2004 Lakeville Sand & Gravel 7.00 1
11/08/2004 11/09/2004 Lakeville Sand & Gravel 14.00 1
12/10/2003 12/10/2003 Lakeville Sand & Gravel 2.00 1
10/08/2003 10/08/2003 Lakeville Sand & Gravel 7.00 1
03/04/2003 03/04/2003 Lakeville Sand & Gravel 6.00 1
11/14/2002 11/14/2002 Lakeville Sand & Gravel 11.00 1
04/09/2002 04/11/2002 Lakeville Sand & Gravel 28.00 1
04/25/2001 04/25/2001 Lakeville Sand & Gravel 9.00 1
03/14/2000 03/14/2000 Lakeville Sand & Gravel 5.00 1