Bice Pit — Inspections

Total: 20 inspections

Begin End Operator Hours Inspectors
08/22/2012 08/22/2012 Bice Gravel Mine 2.75 1
10/26/2011 10/26/2011 Bice Gravel Mine 2.75 1
08/08/2011 08/09/2011 Bice Gravel Mine 14.25 1
10/20/2009 10/20/2009 Bice Gravel Mine 12.25 1
08/04/2009 08/05/2009 Bice Gravel Mine 6.75 1
06/22/2009 06/23/2009 Bice Gravel Mine 3.00 1
11/29/2007 11/29/2007 Bice Gravel Mine 2.25 1
10/29/2007 10/31/2007 Bice Gravel Mine 8.50 1
08/02/2007 08/02/2007 Bice Gravel Mine 3.25 1
07/18/2007 07/19/2007 Bice Gravel Mine 10.75 1
08/22/2006 08/23/2006 Bice Gravel Mine 16.00 1
08/05/2005 08/05/2005 Bice Gravel Mine 4.25 1
07/20/2005 07/21/2005 Bice Gravel Mine 11.50 1
08/17/2004 08/17/2004 Bice Gravel Mine 7.00 1
09/02/2003 09/03/2003 Bice Gravel Mine 16.00 2
08/21/2003 08/21/2003 Bice Gravel Mine 20.00 2
05/20/2002 05/20/2002 Bice Gravel Mine 5.00 1
05/09/2002 05/09/2002 Bice Gravel Mine 6.00 1
04/25/2002 04/25/2002 Bice Gravel Mine 3.00 1
07/26/2000 07/26/2000 William Wust & Sons 6.00 1