Bowser Mine — Inspections

Total: 12 inspections

Begin End Operator Hours Inspectors
12/18/2025 12/18/2025 Neiswonger Construction Inc 4.25 1
10/20/2025 10/21/2025 Neiswonger Construction Inc 36.00 2
09/16/2025 09/16/2025 Neiswonger Construction Inc 3.00 1
09/04/2025 09/04/2025 Neiswonger Construction Inc 7.25 1
03/24/2025 03/25/2025 Neiswonger Construction Inc 11.25 1
02/13/2025 03/19/2025 Neiswonger Construction Inc 24.75 1
01/15/2025 01/16/2025 Neiswonger Construction Inc 19.50 1
08/15/2024 09/25/2024 Neiswonger Construction Inc 34.50 1
04/30/2024 06/04/2024 Neiswonger Construction Inc 55.50 1
10/23/2023 11/22/2023 Neiswonger Construction Inc 55.00 2
07/05/2023 07/10/2023 Neiswonger Construction Inc 11.50 1
01/30/2023 02/23/2023 Neiswonger Construction Inc 51.00 2