Brandenburg Quarry — Inspections

Total: 15 inspections

Begin End Operator Hours Inspectors
12/05/2007 12/05/2007 Vulcan Constr. Materials L.P. 9.50 1
10/16/2006 10/16/2006 Vulcan Constr. Materials L.P. 7.00 1
10/03/2006 10/04/2006 Vulcan Constr. Materials L.P. 23.50 1
02/13/2006 02/16/2006 Vulcan Constr. Materials L.P. 30.50 1
05/17/2005 05/17/2005 Vulcan Constr. Materials L.P. 1.25 1
05/16/2005 05/17/2005 Vulcan Constr. Materials L.P. 16.75 1
10/27/2003 10/28/2003 Vulcan Constr. Materials L.P. 11.00 1
12/11/2002 12/11/2002 Vulcan Materials Co 0.00 0
10/17/2002 10/17/2002 Vulcan Materials Co 4.00 1
08/07/2002 08/07/2002 Vulcan Materials Co 11.00 1
11/20/2000 11/21/2000 Vulcan Construction Materials,... 8.00 1
11/09/2000 11/09/2000 Vulcan Construction Materials,... 3.00 1
11/07/2000 11/08/2000 Vulcan Construction Materials,... 2.00 1
10/17/2000 10/18/2000 Vulcan Construction Materials,... 12.00 1
03/27/2000 03/29/2000 Vulcan Construction Materials,... 10.00 1