CCU Patterson Strip — Inspections

Total: 15 inspections

Begin End Operator Hours Inspectors
05/22/2024 05/22/2024 CCU Coal and Construction LLC 3.00 1
11/08/2023 02/07/2024 CCU Coal and Construction LLC 41.50 1
05/31/2023 07/11/2023 CCU Coal and Construction LLC 16.00 1
04/07/2023 08/24/2023 CCU Coal and Construction LLC 39.50 2
10/03/2022 03/10/2023 CCU Coal and Construction LLC 41.00 1
04/12/2022 09/20/2022 CCU Coal and Construction LLC 35.50 1
02/08/2022 03/27/2022 CCU Coal and Construction LLC 36.50 1
08/24/2021 08/24/2021 Kimble Clay & Limestone 3.00 1
04/13/2021 04/13/2021 Kimble Clay & Limestone 2.50 1
03/31/2021 03/31/2021 Kimble Clay & Limestone 3.00 1
09/29/2020 09/29/2020 Kimble Clay & Limestone 3.50 1
05/17/2019 09/25/2019 Kimble Clay & Limestone 5.50 2
01/22/2019 03/21/2019 Kimble Clay & Limestone 11.50 1
02/16/2017 02/17/2017 Kimble Clay & Limestone 3.50 1
06/09/2016 06/09/2016 Kimble Clay & Limestone 22.50 2