Clarks Grove Pit — Inspections
Total: 16 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 09/13/2011 | 09/13/2011 | Owatonna Concrete Products LLC | 4.00 | 1 |
| 06/07/2011 | 06/07/2011 | Owatonna Concrete Products LLC | 1.50 | 1 |
| 07/26/2010 | 07/26/2010 | Owatonna Concrete Products LLC | 4.50 | 1 |
| 09/15/2009 | 09/15/2009 | Owatonna Concrete Products LLC | 1.75 | 1 |
| 10/30/2007 | 10/30/2007 | Randall Ready Mix LLC | 4.25 | 1 |
| 05/02/2007 | 05/03/2007 | Randall Ready Mix LLC | 7.50 | 1 |
| 12/13/2006 | 12/13/2006 | Randall Ready Mix LLC | 7.50 | 1 |
| 06/07/2006 | 06/07/2006 | Randall Ready Mix LLC | 8.25 | 1 |
| 05/17/2005 | 05/17/2005 | Clarks Grove Ready Mix LLC | 2.50 | 1 |
| 10/14/2003 | 10/14/2003 | Clarks Grove Ready Mix LLC | 9.00 | 1 |
| 08/19/2003 | 08/19/2003 | Clarks Grove Ready Mix LLC | 6.00 | 1 |
| 01/28/2003 | 01/28/2003 | Clarks Grove Ready Mix LLC | 11.00 | 1 |
| 10/23/2001 | 10/23/2001 | Clarks Grove Ready Mix LLC | 26.00 | 1 |
| 05/02/2001 | 05/02/2001 | Clarks Grove Ready Mix LLC | 7.00 | 1 |
| 07/11/2000 | 07/13/2000 | Clarks Grove Ready Mix LLC | 4.00 | 1 |
| 05/31/2000 | 06/02/2000 | Clarks Grove Ready Mix LLC | 25.00 | 1 |