COX QUARRY — Inspections

Total: 24 inspections

Begin End Operator Hours Inspectors
03/15/2007 03/15/2007 A J Crushing Inc 5.50 1
07/21/2006 07/25/2006 A J Crushing Inc 12.50 1
02/27/2006 03/01/2006 A J Crushing Inc 15.25 1
01/12/2006 01/12/2006 A J Crushing Inc 2.50 1
08/01/2005 08/01/2005 A J Crushing Inc 2.50 1
05/13/2005 05/13/2005 A J Crushing Inc 2.50 1
05/12/2005 05/13/2005 A J Crushing Inc 14.00 1
01/12/2005 01/12/2005 A J Crushing Inc 6.00 1
10/21/2004 10/21/2004 A J Crushing Inc 12.00 1
04/26/2004 04/27/2004 A J Crushing Inc 21.00 1
01/08/2004 01/08/2004 A J Crushing Inc 5.00 1
12/16/2003 12/16/2003 A J Crushing Inc 10.00 1
12/10/2003 12/10/2003 A J Crushing Inc 20.00 2
09/10/2003 09/10/2003 A J Crushing Inc 13.00 1
08/07/2003 08/07/2003 A J Crushing Inc 2.00 1
02/25/2003 02/27/2003 A J Crushing Inc 20.00 1
04/18/2002 04/18/2002 A J Crushing Inc 7.00 1
03/20/2002 03/20/2002 A J Crushing Inc 5.00 1
12/18/2001 12/18/2001 A J Crushing Inc 6.00 1
08/29/2001 08/29/2001 A J Crushing Inc 7.00 1
06/04/2001 06/06/2001 A J Crushing Inc 20.00 2
02/05/2001 02/05/2001 A J Crushing Inc 3.00 1
06/12/2000 06/13/2000 A J Crushing Inc 12.00 1
04/13/2000 04/14/2000 A J Crushing Inc 18.00 1