| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 07/26/2016 | 10/31/2016 | Laredo Paving Inc | 41.25 | 1 |
| 08/04/2014 | 08/07/2014 | Laredo Paving Inc | 27.00 | 1 |
| 06/03/2013 | 06/03/2013 | Laredo Paving Inc | 1.25 | 1 |
| 03/05/2013 | 03/06/2013 | Laredo Paving Inc | 13.50 | 1 |
| 10/03/2012 | 10/04/2012 | Laredo Paving Inc | 1.50 | 1 |
| 07/10/2012 | 07/11/2012 | Laredo Paving Inc | 33.00 | 1 |
| 01/19/2012 | 01/20/2012 | Laredo Paving Inc | 15.00 | 1 |
| 03/29/2011 | 03/29/2011 | Laredo Paving Inc | 7.00 | 1 |
| 02/28/2011 | 02/28/2011 | Laredo Paving Inc | 4.50 | 1 |
| 02/23/2011 | 02/24/2011 | Laredo Paving Inc | 11.50 | 1 |
| 11/16/2009 | 11/17/2009 | Laredo Paving Inc | 19.50 | 1 |
| 10/26/2009 | 10/28/2009 | Laredo Paving Inc | 11.25 | 1 |
| 10/19/2009 | 10/21/2009 | Laredo Paving Inc | 16.00 | 1 |
| 11/05/2008 | 11/06/2008 | Laredo Paving Inc | 4.75 | 1 |
| 06/10/2008 | 06/10/2008 | Laredo Paving Inc | 6.00 | 1 |
| 01/22/2008 | 01/22/2008 | Laredo Paving Inc | 3.00 | 1 |
| 03/20/2007 | 03/21/2007 | Laredo Paving Inc | 9.00 | 1 |
| 08/15/2006 | 08/16/2006 | Laredo Paving Inc | 12.00 | 1 |
| 06/30/2005 | 06/30/2005 | Laredo Paving Inc | 11.00 | 1 |
| 02/16/2005 | 02/16/2005 | Laredo Paving Inc | 4.00 | 1 |
| 06/22/2004 | 06/22/2004 | Laredo Paving Inc | 31.00 | 2 |
| 07/09/2003 | 07/09/2003 | Laredo Paving Inc | 8.00 | 1 |
| 10/15/2002 | 10/15/2002 | Laredo Paving Inc | 2.00 | 1 |
| 07/09/2002 | 07/10/2002 | Laredo Paving Inc | 27.00 | 1 |
| 05/16/2001 | 05/16/2001 | Laredo Paving Inc | 32.00 | 1 |
| 05/08/2001 | 05/09/2001 | Laredo Paving Inc | 22.00 | 1 |
| 08/15/2000 | 08/16/2000 | Laredo Paving Inc | 19.00 | 1 |
| 05/17/2000 | 05/23/2000 | Laredo Paving Inc | 33.00 | 1 |