CULLOR PORTABLE — Inspections

Total: 16 inspections

Begin End Operator Hours Inspectors
04/06/2006 04/06/2006 Ash Grove Aggregates Inc 2.00 1
02/24/2006 02/24/2006 Ash Grove Aggregates Inc 4.75 1
02/16/2006 02/16/2006 Ash Grove Aggregates Inc 8.50 1
09/06/2005 09/08/2005 Ash Grove Aggregates Inc 27.50 1
02/23/2005 02/23/2005 Ash Grove Aggregates Inc 13.00 1
08/03/2004 08/03/2004 Ash Grove Aggregates Inc 6.00 1
06/16/2004 06/17/2004 Ash Grove Aggregates Inc 39.00 2
03/30/2004 03/31/2004 Ash Grove Aggregates Inc 8.00 1
03/29/2004 03/30/2004 Ash Grove Aggregates Inc 17.00 1
10/22/2003 10/23/2003 Ash Grove Aggregates Inc 21.00 1
09/17/2003 09/18/2003 Ash Grove Aggregates Inc 15.00 1
01/30/2003 02/03/2003 Ash Grove Aggregates Inc 48.00 1
08/21/2002 08/22/2002 Ash Grove Aggregates Inc 18.00 1
01/08/2002 01/10/2002 Ash Grove Aggregates Inc 40.00 1
03/09/2000 03/09/2000 Ash Grove Aggregates Inc 4.00 1
01/25/2000 01/26/2000 Ash Grove Aggregates Inc 20.00 1