Dover Sand Plant — Inspections

Total: 65 inspections

Begin End Operator Hours Inspectors
11/22/2005 11/22/2005 Dolese Bros Co 6.00 1
07/18/2005 07/18/2005 Dolese Bros Co 9.50 1
11/05/2004 11/05/2004 Dolese Bros Co 3.00 1
10/26/2004 10/27/2004 Dolese Bros Co 40.00 2
03/30/2004 03/30/2004 Dolese Bros Co 9.00 1
05/08/2003 05/08/2003 Dolese Bros Co 2.00 1
05/05/2003 05/08/2003 Dolese Bros Co 9.00 1
05/05/2003 05/05/2003 Dolese Bros Co 1.00 1
10/30/2002 10/31/2002 Dolese Bros Co 11.00 1
07/23/2002 07/23/2002 Dolese Bros Co 7.00 1
10/18/2001 10/18/2001 Dolese Bros Co 16.00 2
08/06/2001 08/09/2001 Dolese Bros Co 0.00 0
04/12/2001 04/12/2001 Dolese Bros Co 7.00 1
08/30/2000 08/30/2000 Dolese Bros Co 0.00 0
03/08/2000 03/08/2000 Dolese Bros Co 6.00 1