| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 08/06/2025 | 08/06/2025 | Presby Construction, Inc. | 4.50 | 1 |
| 08/22/2024 | 08/23/2024 | Presby Construction, Inc. | 4.00 | 1 |
| 08/04/2024 | 08/07/2024 | Presby Construction, Inc. | 4.75 | 1 |
| 05/30/2023 | 06/06/2023 | Presby Construction, Inc. | 4.00 | 1 |
| 09/07/2022 | 09/07/2022 | Presby Construction, Inc. | 4.00 | 1 |
| 06/15/2021 | 06/17/2021 | Presby Construction, Inc. | 7.75 | 1 |
| 07/08/2020 | 07/09/2020 | Presby Construction, Inc. | 5.00 | 1 |
| 08/21/2019 | 08/22/2019 | Presby Construction, Inc. | 3.50 | 1 |
| 08/14/2018 | 08/15/2018 | Presby Construction, Inc. | 4.50 | 1 |
| 06/06/2017 | 06/07/2017 | Presby Construction, Inc. | 4.75 | 1 |
| 09/07/2016 | 09/07/2016 | Presby Construction, Inc. | 10.50 | 1 |
| 06/29/2015 | 07/02/2015 | Presby Construction, Inc. | 3.25 | 1 |
| 09/17/2014 | 09/18/2014 | Presby Construction, Inc. | 18.25 | 1 |
| 05/14/2013 | 05/15/2013 | Presby Construction, Inc. | 7.25 | 1 |
| 10/01/2012 | 10/02/2012 | Presby Construction, Inc. | 6.00 | 1 |
| 06/18/2012 | 06/18/2012 | Presby Construction, Inc. | 6.50 | 1 |
| 06/28/2010 | 06/28/2010 | Presby Construction, Inc. | 6.00 | 1 |
| 05/25/2010 | 05/26/2010 | Presby Construction, Inc. | 7.00 | 1 |
| 02/22/2010 | 02/23/2010 | Presby Construction, Inc. | 8.00 | 1 |
| 08/25/2009 | 08/26/2009 | Presby Construction, Inc. | 20.00 | 1 |
| 04/01/2008 | 04/01/2008 | Presby Construction, Inc. | 3.00 | 1 |
| 03/27/2008 | 03/27/2008 | Presby Construction, Inc. | 7.00 | 1 |
| 03/18/2008 | 03/20/2008 | Presby Construction, Inc. | 18.00 | 1 |
| 09/27/2007 | 09/27/2007 | Presby Construction, Inc. | 5.50 | 2 |
| 07/19/2006 | 07/20/2006 | Presby Construction, Inc. | 16.50 | 1 |