Total: 27 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 10/31/2023 | 11/01/2023 | Holcim-WCR, Inc. | 17.50 | 1 |
| 06/07/2023 | 06/08/2023 | Holcim-WCR, Inc. | 17.75 | 1 |
| 02/14/2023 | 02/16/2023 | Holcim-WCR, Inc. | 14.50 | 1 |
| 05/11/2022 | 05/13/2022 | Holcim-WCR, Inc. | 12.00 | 1 |
| 10/26/2021 | 10/27/2021 | Holcim-WCR, Inc. | 5.00 | 1 |
| 04/20/2021 | 04/22/2021 | Holcim-WCR, Inc. | 27.50 | 1 |
| 06/04/2009 | 06/05/2009 | Holcim-WCR, Inc. | 15.25 | 1 |
| 01/08/2009 | 01/08/2009 | Holcim-WCR, Inc. | 3.75 | 1 |
| 12/16/2008 | 12/17/2008 | Holcim-WCR, Inc. | 12.50 | 1 |
| 05/27/2008 | 05/28/2008 | Holcim-WCR, Inc. | 5.00 | 1 |
| 05/15/2008 | 05/20/2008 | Holcim-WCR, Inc. | 29.00 | 1 |
| 02/20/2008 | 02/20/2008 | Holcim-WCR, Inc. | 13.00 | 1 |
| 01/08/2008 | 01/09/2008 | Holcim-WCR, Inc. | 1.75 | 1 |
| 02/21/2007 | 02/22/2007 | Holcim-WCR, Inc. | 29.00 | 1 |
| 09/18/2006 | 09/18/2006 | Holcim-WCR, Inc. | 6.00 | 1 |
| 02/16/2006 | 02/17/2006 | Holcim-WCR, Inc. | 15.00 | 1 |
| 12/16/2005 | 12/16/2005 | Holcim-WCR, Inc. | 8.00 | 1 |
| 12/07/2005 | 12/07/2005 | Holcim-WCR, Inc. | 2.00 | 1 |
| 05/10/2005 | 05/12/2005 | Holcim-WCR, Inc. | 29.00 | 1 |
| 08/03/2004 | 08/04/2004 | Holcim-WCR, Inc. | 11.00 | 1 |
| 02/12/2004 | 02/13/2004 | Holcim-WCR, Inc. | 12.00 | 1 |
| 09/10/2003 | 09/10/2003 | Holcim-WCR, Inc. | 4.00 | 1 |
| 02/26/2003 | 02/28/2003 | Holcim-WCR, Inc. | 11.00 | 1 |
| 08/20/2002 | 08/21/2002 | Holcim-WCR, Inc. | 10.00 | 1 |
| 08/22/2001 | 08/22/2001 | Holcim-WCR, Inc. | 1.00 | 1 |
| 01/11/2001 | 01/11/2001 | Holcim-WCR, Inc. | 3.00 | 1 |
| 01/11/2001 | 01/11/2001 | Holcim-WCR, Inc. | 5.00 | 1 |