J & L Gravel — Inspections
Total: 14 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 02/05/2016 | 02/05/2016 | Talley Construction | 3.00 | 1 |
| 01/12/2016 | 01/14/2016 | Talley Construction | 11.50 | 1 |
| 01/12/2016 | 01/13/2016 | Talley Construction | 0.50 | 1 |
| 04/30/2015 | 04/30/2015 | Talley Construction | 7.50 | 1 |
| 02/19/2015 | 02/20/2015 | Talley Construction | 9.75 | 1 |
| 02/19/2015 | 02/19/2015 | Talley Construction | 0.25 | 1 |
| 07/09/2014 | 07/10/2014 | Talley Construction | 14.25 | 1 |
| 01/09/2014 | 01/10/2014 | Talley Construction | 11.50 | 1 |
| 05/06/2013 | 05/06/2013 | Talley Construction | 7.00 | 1 |
| 04/03/2012 | 04/03/2012 | Talley Construction | 3.50 | 1 |
| 03/22/2012 | 03/22/2012 | Talley Construction | 14.00 | 1 |
| 02/15/2011 | 02/16/2011 | Talley Construction | 12.50 | 1 |
| 09/08/2010 | 09/08/2010 | Talley Construction | 11.50 | 1 |
| 11/05/2009 | 11/09/2009 | Talley Construction | 20.00 | 1 |