Jennings Pond Road Mine — Inspections

Total: 11 inspections

Begin End Operator Hours Inspectors
10/09/2025 10/09/2025 Grade A Construction LLC 8.00 1
04/29/2025 04/29/2025 Grade A Construction LLC 10.50 1
01/14/2025 01/16/2025 Grade A Construction LLC 16.75 1
06/20/2024 07/18/2024 Grade A Construction LLC 4.25 1
04/30/2024 05/03/2024 Grade A Construction LLC 7.75 1
04/25/2024 04/25/2024 Grade A Construction LLC 12.00 1
02/21/2024 02/23/2024 Grade A Construction LLC 7.75 1
09/11/2023 09/14/2023 Grade A Construction LLC 12.75 2
06/07/2023 07/25/2023 Grade A Construction LLC 41.00 1
06/07/2023 08/03/2023 Grade A Construction LLC 15.75 1