K500 — Inspections
Total: 12 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 04/09/2025 | 04/10/2025 | Northland Constrs. of Duluth | 9.00 | 1 |
| 05/22/2024 | 05/22/2024 | Northland Constrs. of Duluth | 0.75 | 1 |
| 05/07/2024 | 05/13/2024 | Northland Constrs. of Duluth | 12.50 | 1 |
| 06/06/2023 | 06/07/2023 | Northland Constructors of Dulu... | 12.75 | 1 |
| 05/17/2023 | 05/17/2023 | Northland Constructors of Dulu... | 1.50 | 1 |
| 08/30/2022 | 09/01/2022 | Northland Constructors of Dulu... | 14.50 | 1 |
| 04/21/2021 | 04/22/2021 | Northland Constructors of Dulu... | 19.75 | 1 |
| 08/04/2020 | 08/04/2020 | Northland Constructors of Dulu... | 0.75 | 1 |
| 08/01/2019 | 08/01/2019 | Northland Constructors of Dulu... | 0.50 | 1 |
| 08/08/2018 | 08/08/2018 | Northland Constructors of Dulu... | 1.50 | 1 |
| 08/14/2017 | 08/14/2017 | Northland Constructors of Dulu... | 2.00 | 1 |
| 09/15/2016 | 09/15/2016 | Northland Constructors of Dulu... | 7.25 | 1 |