KONECHNE MINE — Inspections
Total: 12 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 08/19/2025 | 08/19/2025 | GCC Dacotah | 10.25 | 1 |
| 01/22/2025 | 01/23/2025 | GCC Dacotah | 20.50 | 1 |
| 04/02/2024 | 04/02/2024 | GCC Dacotah | 5.75 | 1 |
| 08/02/2021 | 08/02/2021 | GCC Dacotah | 2.75 | 1 |
| 01/08/2021 | 01/08/2021 | GCC Dacotah | 0.50 | 1 |
| 04/28/2020 | 04/29/2020 | GCC Dacotah | 10.50 | 1 |
| 08/20/2019 | 08/20/2019 | GCC Dacotah | 6.50 | 1 |
| 02/13/2019 | 02/15/2019 | GCC Dacotah | 9.25 | 1 |
| 04/26/2018 | 04/30/2018 | GCC Dacotah | 13.75 | 1 |
| 12/14/2017 | 12/14/2017 | GCC Dacotah | 9.50 | 1 |
| 05/31/2017 | 06/01/2017 | GCC Dacotah | 21.25 | 1 |
| 01/26/2017 | 01/27/2017 | GCC Dacotah | 8.25 | 1 |