08/26/2008 08/27/2008 Capitol Aggregates, Inc. 23.00 1
01/17/2008 01/22/2008 Capitol Aggregates, Inc. 16.00 1
04/03/2007 04/05/2007 Capitol Aggregates, Inc. 33.25 1
10/04/2006 10/04/2006 Capitol Aggregates, Inc. 6.00 1
09/28/2006 09/29/2006 Capitol Aggregates, Inc. 12.00 1
03/07/2006 03/08/2006 Capitol Aggregates, Inc. 1.00 1
02/14/2006 02/14/2006 Capitol Aggregates, Inc. 3.50 1
01/31/2006 02/02/2006 Capitol Aggregates, Inc. 22.50 1
09/13/2005 09/13/2005 Capitol Aggregates, Inc. 3.50 1
08/24/2005 08/25/2005 Capitol Aggregates, Inc. 19.50 1
03/10/2005 03/10/2005 Capitol Aggregates, Inc. 4.00 1
01/05/2005 01/05/2005 Capitol Aggregates, Inc. 5.00 1
10/19/2004 10/21/2004 Capitol Aggregates, Inc. 37.00 1