McCook Lime Plant — Inspections
Total: 11 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 01/21/2003 | 01/22/2003 | Vulcan Constr. Materials, L.P. | 38.00 | 1 |
| 10/28/2002 | 10/29/2002 | Vulcan Constr. Materials, L.P. | 22.00 | 1 |
| 10/21/2002 | 10/22/2002 | Vulcan Constr. Materials, L.P. | 15.00 | 1 |
| 09/17/2002 | 09/17/2002 | Vulcan Constr. Materials, L.P. | 3.00 | 1 |
| 08/28/2002 | 09/04/2002 | Vulcan Constr. Materials, L.P. | 32.00 | 1 |
| 07/02/2002 | 09/30/2002 | Vulcan Constr. Materials, L.P. | 40.00 | 2 |
| 01/17/2002 | 01/17/2002 | Vulcan Constr. Materials, L.P. | 7.00 | 1 |
| 01/07/2002 | 01/10/2002 | Vulcan Constr. Materials, L.P. | 39.00 | 1 |
| 08/28/2001 | 08/30/2001 | Vulcan Constr. Materials, L.P. | 55.00 | 2 |
| 04/09/2001 | 04/11/2001 | Vulcan Constr. Materials, L.P. | 39.00 | 1 |
| 04/03/2000 | 04/06/2000 | Vulcan Constr. Materials, L.P. | 41.00 | 1 |