Milennium Blue Quarry — Inspections

Total: 12 inspections

Begin End Operator Hours Inspectors
09/09/2008 09/10/2008 W. L. Carey General Contractor... 10.00 1
09/04/2008 09/04/2008 W. L. Carey General Contractor... 5.75 1
02/07/2007 02/07/2007 W. L. Carey General Contractor... 2.25 1
01/16/2007 01/18/2007 W. L. Carey General Contractor... 25.00 1
08/16/2006 08/16/2006 W. L. Carey General Contractor... 5.50 1
08/02/2006 08/03/2006 W. L. Carey General Contractor... 18.00 1
05/15/2006 05/15/2006 W. L. Carey General Contractor... 1.75 1
04/19/2006 04/19/2006 W. L. Carey General Contractor... 12.00 1
09/29/2005 09/29/2005 W. L. Carey General Contractor... 5.50 1
09/15/2005 09/16/2005 W. L. Carey General Contractor... 37.50 2
03/29/2005 03/29/2005 W. L. Carey General Contractor... 11.75 1
09/14/2004 09/15/2004 W. L. Carey General Contractor... 22.00 1