Begin End Operator Hours Inspectors
01/25/2006 02/28/2006 Dana Mining Company Inc 0.50 1
10/12/2005 12/06/2005 Dana Mining Company Inc 1.00 1
09/21/2005 09/29/2005 Dana Mining Company Inc 1.00 1
05/08/2002 06/19/2002 Millfall Mining Inc 24.50 1
03/07/2002 04/11/2002 Millfall Mining Inc 26.00 1
01/29/2002 03/25/2002 Millfall Mining Inc 69.00 2
12/03/2001 12/04/2001 Millfall Mining Inc 21.00 1
11/26/2001 01/02/2002 Millfall Mining Inc 88.00 1
11/06/2001 11/15/2001 Millfall Mining Inc 23.00 1
07/24/2001 09/04/2001 Millfall Mining Inc 31.00 2
01/26/2000 01/26/2000 Island Fork Construction Ltd 8.00 1
01/12/2000 03/27/2000 Island Fork Construction Ltd 18.50 1