Begin End Operator Hours Inspectors
02/06/2007 02/09/2007 Columbia Rock & Aggregates Inc 45.00 1
07/18/2006 07/19/2006 Columbia Rock & Aggregates Inc 20.00 1
07/12/2006 07/27/2006 Columbia Rock & Aggregates Inc 41.00 1
12/13/2005 12/14/2005 Columbia Rock & Aggregates Inc 19.00 1
06/20/2005 06/22/2005 Columbia Rock & Aggregates Inc 14.00 1
03/29/2005 03/29/2005 Columbia Rock & Aggregates Inc 5.00 1
01/19/2005 01/28/2005 Columbia Rock & Aggregates Inc 33.00 1
05/12/2004 05/13/2004 Columbia Rock & Aggregates Inc 16.00 1
12/04/2003 12/05/2003 Columbia Rock & Aggregates Inc 12.00 1
07/24/2003 07/24/2003 Columbia Rock & Aggregates Inc 4.00 1
07/22/2003 07/24/2003 Columbia Rock & Aggregates Inc 29.00 1
03/12/2003 03/14/2003 Columbia Rock & Aggregates Inc 14.00 1
10/22/2002 10/22/2002 Columbia Rock & Aggregates Inc 2.00 1
07/25/2002 07/25/2002 Columbia Rock & Aggregates Inc 1.00 1
07/17/2002 07/18/2002 Columbia Rock & Aggregates Inc 35.00 1
01/08/2002 01/09/2002 Columbia Rock & Aggregates Inc 20.00 2
08/22/2001 09/12/2001 Columbia Rock & Aggregates Inc 31.00 1
09/25/2000 09/25/2000 Columbia Rock & Aggregates Inc 6.00 1
08/03/2000 08/16/2000 Columbia Rock & Aggregates Inc 41.00 1