Total: 21 inspections

Begin End Operator Hours Inspectors
11/29/2010 11/29/2010 Dakota Earthworks Inc 2.00 1
06/29/2010 06/29/2010 Dakota Earthworks Inc 1.25 1
05/13/2010 05/13/2010 Dakota Earthworks Inc 1.25 1
05/06/2010 05/06/2010 Dakota Earthworks Inc 6.25 1
05/03/2010 05/04/2010 Dakota Earthworks Inc 9.50 1
04/21/2010 04/21/2010 Dakota Earthworks Inc 15.75 1
08/31/2009 08/31/2009 Dakota Earthworks Inc 1.00 1
06/30/2009 06/30/2009 Dakota Earthworks Inc 12.50 1
06/23/2008 06/24/2008 Dakota Earthworks Inc 11.50 1
09/19/2007 09/19/2007 Dakota Earthworks Inc 2.50 1
08/15/2007 08/15/2007 Dakota Earthworks Inc 2.00 1
08/15/2007 08/15/2007 Dakota Earthworks Inc 16.00 1
10/25/2005 10/25/2005 Dakota Earthworks Inc 12.00 1
11/30/2004 12/01/2004 Dakota Earthworks Inc 20.00 1
01/27/2004 01/27/2004 Dakota Earthworks Inc 7.00 1
10/21/2003 10/21/2003 Dakota Earthworks Inc 6.00 1
10/16/2003 10/16/2003 Dakota Earthworks Inc 14.00 2
08/26/2003 08/26/2003 Dakota Earthworks Inc 2.00 1
11/19/2002 11/19/2002 Dakota Earthworks Inc 5.00 1
01/09/2002 01/09/2002 Dakota Earthworks Inc 20.00 2
05/15/2001 05/16/2001 Dakota Earthworks Inc 11.00 1