Begin End Operator Hours Inspectors
12/14/2020 12/23/2020 Harvey Sand & Gravel Inc 1.00 1
08/07/2018 08/09/2018 Harvey Sand & Gravel Inc 6.75 1
07/10/2018 07/10/2018 Harvey Sand & Gravel Inc 19.75 1
08/08/2017 08/09/2017 Harvey Sand & Gravel Inc 1.50 1
09/09/2015 09/09/2015 Harvey Sand & Gravel Inc 1.25 1
05/20/2015 05/20/2015 Harvey Sand & Gravel Inc 0.25 1
05/20/2015 05/20/2015 Harvey Sand & Gravel Inc 14.00 1
07/09/2014 07/09/2014 Harvey Sand & Gravel Inc 18.75 1
04/04/2013 04/04/2013 Harvey Sand & Gravel Inc 21.75 1
11/09/2011 11/09/2011 Harvey Sand & Gravel Inc 16.25 1
03/02/2011 03/02/2011 Harvey Sand & Gravel Inc 5.50 1
10/05/2010 10/05/2010 Harvey Sand & Gravel Inc 17.00 1
10/27/2009 10/27/2009 Harvey Sand & Gravel Inc 18.50 1
08/31/2009 08/31/2009 Harvey Sand & Gravel Inc 2.00 1
05/19/2009 05/20/2009 Harvey Sand & Gravel Inc 29.50 1
10/30/2006 11/02/2006 Harvey Sand & Gravel Inc 23.50 2
09/26/2006 09/27/2006 Harvey Sand & Gravel Inc 20.00 1
07/26/2005 07/26/2005 Harvey Sand & Gravel Inc 8.75 1
08/25/2004 08/26/2004 Harvey Sand & Gravel Inc 14.00 1
07/09/2002 07/11/2002 Harvey Sand & Gravel Inc 12.00 1
05/09/2000 05/09/2000 Harvey Sand & Gravel Inc 7.00 1
04/05/2000 04/05/2000 Harvey Sand & Gravel Inc 7.00 1