PORTABLE CRUSHER 05 — Inspections
Total: 10 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 12/05/2005 | 12/06/2005 | CPC Southwest Materials Inc | 8.00 | 1 |
| 08/17/2005 | 08/18/2005 | Tucson Ready Mix Inc | 8.75 | 1 |
| 11/17/2004 | 11/18/2004 | Tucson Ready Mix Inc | 9.00 | 1 |
| 07/20/2004 | 07/20/2004 | Tucson Ready Mix Inc | 4.00 | 1 |
| 07/07/2004 | 07/09/2004 | Tucson Ready Mix Inc | 7.00 | 1 |
| 03/02/2004 | 03/02/2004 | Tucson Ready Mix Inc | 10.00 | 1 |
| 04/17/2003 | 04/21/2003 | Tucson Ready Mix Inc | 22.00 | 2 |
| 08/21/2002 | 08/22/2002 | Tucson Ready Mix Inc | 12.00 | 2 |
| 04/24/2001 | 04/24/2001 | Tucson Ready Mix Inc | 9.00 | 2 |
| 03/02/2000 | 05/31/2000 | Tucson Ready Mix Inc | 26.00 | 1 |