Portable Crusher — Inspections
Total: 23 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 09/29/2022 | 09/29/2022 | D. R. Billings, Inc. | 1.00 | 1 |
| 07/03/2017 | 07/05/2017 | D. R. Billings, Inc. | 12.50 | 1 |
| 11/16/2016 | 11/16/2016 | D. R. Billings, Inc. | 4.75 | 1 |
| 05/13/2014 | 05/13/2014 | D. R. Billings, Inc. | 4.75 | 1 |
| 12/17/2012 | 12/18/2012 | D. R. Billings, Inc. | 1.75 | 1 |
| 10/15/2012 | 10/23/2012 | D. R. Billings, Inc. | 17.75 | 1 |
| 10/09/2012 | 10/12/2012 | D. R. Billings, Inc. | 31.00 | 1 |
| 05/03/2012 | 05/03/2012 | D. R. Billings, Inc. | 1.50 | 1 |
| 12/19/2011 | 01/05/2012 | D. R. Billings, Inc. | 2.75 | 1 |
| 06/02/2011 | 06/02/2011 | D. R. Billings, Inc. | 1.00 | 1 |
| 05/25/2011 | 05/26/2011 | D. R. Billings, Inc. | 12.50 | 1 |
| 05/31/2005 | 05/31/2005 | D. R. Billings, Inc. | 3.50 | 2 |
| 09/20/2004 | 09/20/2004 | D. R. Billings, Inc. | 3.00 | 1 |
| 08/18/2004 | 08/19/2004 | D. R. Billings, Inc. | 12.00 | 1 |
| 08/10/2004 | 08/10/2004 | D. R. Billings, Inc. | 2.00 | 1 |
| 06/24/2004 | 06/24/2004 | D. R. Billings, Inc. | 1.00 | 1 |
| 05/13/2004 | 05/13/2004 | D. R. Billings, Inc. | 5.00 | 1 |
| 10/08/2003 | 10/08/2003 | D. R. Billings, Inc. | 3.00 | 1 |
| 06/03/2003 | 06/04/2003 | D. R. Billings, Inc. | 22.00 | 2 |
| 11/07/2002 | 11/07/2002 | D. R. Billings, Inc. | 4.00 | 1 |
| 05/23/2002 | 05/23/2002 | D. R. Billings, Inc. | 3.00 | 1 |
| 09/27/2001 | 09/27/2001 | D. R. Billings, Inc. | 4.00 | 1 |
| 08/09/2000 | 08/09/2000 | D. R. Billings, Inc. | 8.00 | 1 |