PORTABLE CRUSHER #2 — Inspections
Total: 13 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 03/13/2006 | 03/13/2006 | Konitz Contracting Inc | 4.00 | 1 |
| 11/07/2005 | 11/07/2005 | Konitz Contracting Inc | 3.75 | 1 |
| 10/27/2005 | 11/01/2005 | Konitz Contracting Inc | 17.50 | 1 |
| 08/15/2005 | 08/17/2005 | Konitz Contracting Inc | 23.50 | 1 |
| 09/07/2004 | 09/14/2004 | Konitz Contracting Inc | 54.00 | 2 |
| 10/21/2003 | 10/21/2003 | Konitz Contracting Inc | 2.00 | 1 |
| 08/13/2003 | 08/14/2003 | Konitz Contracting Inc | 17.00 | 1 |
| 04/15/2003 | 04/17/2003 | Konitz Contracting Inc | 28.00 | 1 |
| 10/21/2002 | 10/21/2002 | Konitz Contracting Inc | 3.00 | 1 |
| 03/26/2002 | 03/27/2002 | Konitz Contracting Inc | 25.00 | 1 |
| 07/25/2001 | 07/26/2001 | Konitz Contracting Inc | 21.00 | 1 |
| 07/10/2001 | 07/10/2001 | Konitz Contracting Inc | 6.00 | 1 |
| 09/15/2000 | 09/18/2000 | Konitz Contracting Inc | 8.00 | 1 |