Portable Plant — Inspections
Total: 8 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 09/02/2009 | 09/03/2009 | Burns Concrete Inc | 1.50 | 1 |
| 04/15/2009 | 04/15/2009 | Burns Concrete Inc | 10.00 | 1 |
| 03/11/2008 | 03/11/2008 | Burns Concrete Inc | 6.50 | 1 |
| 04/17/2007 | 04/17/2007 | Burns Concrete Inc | 11.00 | 1 |
| 08/01/2006 | 08/01/2006 | Burns Concrete Inc | 10.00 | 1 |
| 12/14/2004 | 12/14/2004 | Burns Concrete Inc | 11.00 | 1 |
| 05/17/2004 | 05/18/2004 | Burns Concrete Inc | 23.00 | 1 |
| 05/11/2004 | 05/11/2004 | Burns Concrete Inc | 0.00 | 0 |