Portable Plant #3 — Inspections
Total: 10 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 08/22/2013 | 08/22/2013 | Reilly Construction Company In... | 7.00 | 1 |
| 09/12/2012 | 09/13/2012 | Reilly Construction Company In... | 29.50 | 1 |
| 08/15/2006 | 08/15/2006 | Reilly Construction Company In... | 4.50 | 1 |
| 08/30/2005 | 08/31/2005 | Reilly Construction Company In... | 9.25 | 1 |
| 09/28/2004 | 09/28/2004 | Reilly Construction Company In... | 7.00 | 1 |
| 09/15/2003 | 09/15/2003 | Reilly Construction Company In... | 1.00 | 1 |
| 08/19/2003 | 08/19/2003 | Reilly Construction Company In... | 6.00 | 1 |
| 06/25/2003 | 06/25/2003 | Reilly Construction Company In... | 5.00 | 1 |
| 09/26/2001 | 09/26/2001 | Reilly Construction Company In... | 2.00 | 1 |
| 04/24/2001 | 04/25/2001 | Reilly Construction Company In... | 10.00 | 1 |