RANDLETT PIT — Inspections

Total: 61 inspections

Begin End Operator Hours Inspectors
02/11/2003 02/11/2003 Tri-County Concrete 3.00 1
10/22/2002 10/22/2002 Tri-County Concrete 3.00 1
05/09/2002 05/09/2002 Tri-County Concrete 8.00 1
04/04/2002 04/04/2002 Tri-County Concrete 6.00 1
01/30/2002 01/31/2002 Tri-County Concrete 18.00 1
08/17/2001 08/17/2001 Tri-County Concrete 2.00 1
07/10/2001 07/12/2001 Tri-County Concrete 44.00 2
05/01/2001 05/01/2001 Tri-County Concrete 4.00 1
04/16/2001 04/18/2001 Tri-County Concrete 19.00 1
01/31/2000 01/31/2000 Tri-County Concrete 6.00 1
01/20/2000 01/21/2000 Tri-County Concrete 11.00 1