Rinker Materials Chino Valley — Inspections
Total: 10 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 10/11/2005 | 10/12/2005 | RINKER MATERIALS | 12.50 | 1 |
| 05/31/2005 | 06/01/2005 | RINKER MATERIALS | 12.00 | 1 |
| 02/27/2004 | 03/05/2004 | Rinker Materials Western Inc. | 7.00 | 1 |
| 05/13/2003 | 05/13/2003 | Rinker Materials Western Inc. | 6.00 | 1 |
| 07/11/2002 | 07/11/2002 | UNITED METRO MATERIALS INC | 2.00 | 1 |
| 04/23/2002 | 04/23/2002 | Meadow Valley Contractors Inc | 2.00 | 1 |
| 04/12/2002 | 04/12/2002 | Meadow Valley Contractors Inc | 8.00 | 1 |
| 09/19/2001 | 09/19/2001 | Meadow Valley Contractors Inc | 4.00 | 1 |
| 06/26/2001 | 06/28/2001 | Meadow Valley Contractors Inc | 20.00 | 2 |
| 04/25/2000 | 04/27/2000 | Meadow Valley Contractors Inc | 24.00 | 1 |