ROBINSON PIT — Inspections
Total: 11 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 03/24/2004 | 03/24/2004 | Clyde Mcmahon Concrete Company | 20.00 | 1 |
| 09/10/2003 | 09/10/2003 | Clyde Mcmahon Concrete Company | 6.00 | 1 |
| 07/16/2003 | 07/16/2003 | Clyde Mcmahon Concrete Company | 10.00 | 1 |
| 05/27/2003 | 05/28/2003 | Clyde Mcmahon Concrete Company | 28.00 | 1 |
| 03/18/2003 | 03/19/2003 | Clyde Mcmahon Concrete Company | 17.00 | 1 |
| 10/15/2002 | 10/15/2002 | Clyde Mcmahon Concrete Company | 2.00 | 1 |
| 07/16/2002 | 07/17/2002 | Clyde Mcmahon Concrete Company | 28.00 | 1 |
| 11/20/2001 | 11/21/2001 | Clyde Mcmahon Concrete Company | 2.00 | 1 |
| 03/28/2001 | 03/29/2001 | Clyde Mcmahon Concrete Company | 6.00 | 1 |
| 01/23/2001 | 01/25/2001 | Clyde Mcmahon Concrete Company | 39.00 | 1 |
| 06/20/2000 | 06/21/2000 | Clyde Mcmahon Concrete Company | 13.00 | 1 |