Screen Plant #2 — Inspections
Total: 24 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 06/26/2012 | 06/26/2012 | Johnson Brothers Contracting,... | 4.50 | 1 |
| 03/01/2011 | 03/01/2011 | Johnson Brothers Contracting,... | 7.00 | 1 |
| 02/09/2011 | 02/09/2011 | Johnson Brothers Contracting,... | 1.00 | 1 |
| 11/02/2010 | 11/03/2010 | Johnson Brothers Contracting,... | 6.25 | 1 |
| 09/22/2010 | 09/24/2010 | Johnson Brothers Contracting,... | 23.50 | 1 |
| 12/14/2009 | 12/15/2009 | Johnson Brothers Contracting,... | 4.25 | 1 |
| 12/03/2009 | 12/08/2009 | Johnson Brothers Contracting,... | 13.00 | 1 |
| 10/19/2009 | 10/19/2009 | Johnson Brothers Contracting,... | 6.25 | 1 |
| 09/24/2009 | 09/24/2009 | Johnson Brothers Contracting,... | 3.75 | 1 |
| 09/21/2009 | 09/22/2009 | Johnson Brothers Contracting,... | 21.25 | 1 |
| 08/25/2009 | 08/25/2009 | Johnson Brothers Contracting,... | 3.25 | 1 |
| 03/25/2008 | 03/25/2008 | Johnson Brothers Contracting,... | 12.50 | 1 |
| 09/10/2007 | 09/11/2007 | Johnson Brothers Contracting,... | 12.00 | 1 |
| 09/05/2007 | 09/07/2007 | Johnson Brothers Contracting,... | 46.50 | 2 |
| 02/14/2007 | 02/15/2007 | Johnson Brothers Contracting,... | 3.50 | 1 |
| 05/09/2006 | 05/10/2006 | Johnson Brothers Contracting,... | 20.50 | 1 |
| 04/13/2005 | 04/13/2005 | Johnson Brothers Contracting,... | 3.50 | 1 |
| 04/06/2005 | 04/07/2005 | Johnson Brothers Contracting,... | 7.50 | 1 |
| 11/04/2004 | 11/04/2004 | Johnson Brothers Contracting,... | 3.00 | 1 |
| 04/29/2004 | 04/29/2004 | Johnson Brothers Contracting,... | 13.00 | 1 |
| 04/21/2004 | 04/22/2004 | Johnson Brothers Contracting,... | 5.00 | 1 |
| 02/19/2004 | 02/19/2004 | Johnson Brothers Contracting,... | 10.00 | 2 |
| 07/22/2003 | 07/23/2003 | Johnson Brothers Contracting,... | 5.00 | 1 |
| 04/18/2002 | 04/18/2002 | Johnson Brothers Contracting,... | 9.00 | 1 |