Sena Pit — Inspections
Total: 12 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 01/07/2009 | 01/07/2009 | Sena Construction | 8.00 | 1 |
| 12/31/2008 | 12/31/2008 | Sena Construction | 8.75 | 1 |
| 10/24/2007 | 10/24/2007 | Sena Construction | 8.00 | 1 |
| 10/22/2007 | 10/22/2007 | Sena Construction | 3.00 | 1 |
| 05/22/2007 | 05/24/2007 | Sena Construction | 24.50 | 1 |
| 08/04/2006 | 08/07/2006 | Sena Construction | 10.25 | 1 |
| 01/23/2006 | 01/23/2006 | Sena Construction | 1.00 | 1 |
| 01/11/2006 | 01/12/2006 | Riverside Constr. Co. Inc | 20.00 | 1 |
| 08/04/2004 | 08/04/2004 | Riverside Constr. Co. Inc | 1.00 | 1 |
| 03/17/2004 | 03/17/2004 | Riverside Constr. Co. Inc | 10.00 | 2 |
| 03/10/2003 | 03/10/2003 | Riverside Constr. Co. Inc | 6.00 | 1 |
| 03/04/2003 | 03/04/2003 | Riverside Constr. Co. Inc | 7.00 | 1 |