Splitt Quarry — Inspections
Total: 15 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 03/03/2014 | 03/04/2014 | B-Y Excavating Inc | 8.00 | 1 |
| 05/20/2013 | 05/21/2013 | B-Y Excavating Inc | 10.25 | 1 |
| 05/20/2013 | 05/20/2013 | B-Y Excavating Inc | 9.25 | 1 |
| 12/27/2012 | 12/27/2012 | B-Y Excavating Inc | 9.00 | 1 |
| 11/29/2012 | 12/03/2012 | B-Y Excavating Inc | 10.00 | 1 |
| 10/30/2012 | 10/30/2012 | B-Y Excavating Inc | 7.50 | 1 |
| 07/10/2012 | 07/11/2012 | B-Y Excavating Inc | 28.50 | 1 |
| 03/06/2012 | 03/06/2012 | B-Y Excavating Inc | 10.25 | 1 |
| 02/27/2012 | 02/29/2012 | B-Y Excavating Inc | 18.75 | 1 |
| 05/25/2011 | 05/26/2011 | B-Y Excavating Inc | 18.00 | 1 |
| 06/01/2010 | 06/01/2010 | B-Y Excavating Inc | 4.00 | 1 |
| 05/24/2010 | 05/24/2010 | B-Y Excavating Inc | 2.75 | 1 |
| 05/19/2010 | 05/20/2010 | B-Y Excavating Inc | 22.50 | 1 |
| 09/23/2009 | 09/23/2009 | B-Y Excavating Inc | 6.50 | 1 |
| 09/17/2009 | 09/17/2009 | B-Y Excavating Inc | 7.50 | 1 |