Total: 13 inspections

Begin End Operator Hours Inspectors
10/13/2005 10/13/2005 Otto Construction Inc 6.00 1
03/29/2005 03/31/2005 Otto Construction Inc 31.00 2
03/17/2005 03/17/2005 Otto Construction Inc 10.00 1
05/05/2004 05/05/2004 Otto Construction Inc 6.00 1
10/21/2003 10/24/2003 Otto Construction Inc 15.00 1
12/05/2002 12/10/2002 Otto Construction Inc 46.00 2
10/22/2002 10/22/2002 Otto Construction Inc 4.00 1
09/05/2001 09/06/2001 Otto Construction Inc 21.00 2
08/02/2001 08/02/2001 Otto Construction Inc 3.00 1
07/31/2001 07/31/2001 Otto Construction Inc 4.00 1
09/22/2000 09/22/2000 Otto Construction Inc 3.00 1
09/14/2000 09/14/2000 Otto Construction Inc 11.00 1
09/12/2000 09/12/2000 Otto Construction Inc 5.00 1