Thompson Creek Mine — Inspections
Total: 112 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 08/12/2003 | 08/13/2003 | Thompson Creek Mining Company | 33.00 | 1 |
| 07/23/2003 | 07/23/2003 | Thompson Creek Mining Company | 12.00 | 1 |
| 07/22/2003 | 07/22/2003 | Thompson Creek Mining Company | 27.00 | 1 |
| 07/07/2003 | 07/30/2003 | Thompson Creek Mining Company | 119.00 | 1 |
| 11/04/2002 | 11/14/2002 | Thompson Creek Mining Company | 99.00 | 2 |
| 09/11/2002 | 09/19/2002 | Thompson Creek Mining Company | 75.00 | 1 |
| 04/09/2002 | 04/25/2002 | Thompson Creek Mining Company | 107.00 | 2 |
| 09/24/2001 | 09/24/2001 | Thompson Creek Mining Company | 9.00 | 1 |
| 08/27/2001 | 09/13/2001 | Thompson Creek Mining Company | 105.00 | 1 |
| 04/17/2001 | 04/26/2001 | Thompson Creek Mining Company | 83.00 | 1 |
| 01/18/2001 | 01/18/2001 | Thompson Creek Mining Company | 23.00 | 1 |
| 02/01/2000 | 03/08/2000 | Thompson Creek Mining Company | 128.00 | 1 |