TORO QUARRY — Inspections

Total: 24 inspections

Begin End Operator Hours Inspectors
04/01/2010 04/01/2010 CEMEX Construction Materials S... 23.00 1
11/04/2009 11/04/2009 CEMEX Construction Materials S... 2.50 1
04/09/2009 04/09/2009 CEMEX Construction Materials S... 6.00 1
04/02/2009 04/02/2009 CEMEX Construction Materials S... 7.00 1
11/03/2008 11/04/2008 CEMEX Construction Materials S... 8.00 1
10/29/2008 10/30/2008 CEMEX Construction Materials S... 18.00 1
10/22/2008 10/22/2008 CEMEX Construction Materials S... 3.00 1
02/08/2006 02/08/2006 CEMEX Construction Materials L... 0.00 0
02/08/2006 02/08/2006 CEMEX Construction Materials L... 9.00 1
07/18/2005 07/18/2005 CEMEX Construction Materials L... 7.00 1
07/12/2005 07/13/2005 CEMEX Construction Materials L... 30.00 1
01/25/2005 01/25/2005 Jobe Concrete Products Inc 14.00 1
04/06/2004 04/07/2004 Jobe Concrete Products Inc 31.00 1
04/06/2004 04/06/2004 Jobe Concrete Products Inc 3.00 1
11/04/2003 11/04/2003 Jobe Concrete Products Inc 22.00 1
09/02/2003 09/03/2003 Jobe Concrete Products Inc 14.00 1
04/24/2003 04/24/2003 Jobe Concrete Products Inc 17.00 1
10/16/2002 10/16/2002 Jobe Concrete Products Inc 3.00 1
08/06/2002 08/06/2002 Jobe Concrete Products Inc 22.00 1
01/08/2002 01/09/2002 Jobe Concrete Products Inc 15.00 1
05/22/2001 05/23/2001 Jobe Concrete Products Inc 28.00 1
05/21/2001 05/21/2001 Jobe Concrete Products Inc 10.00 1
07/18/2000 07/19/2000 Jobe Concrete Products Inc 31.00 1
01/05/2000 01/06/2000 Jobe Concrete Products Inc 14.00 1