West Farm Pit-Wash Plant — Inspections

Total: 10 inspections

Begin End Operator Hours Inspectors
01/30/2019 02/01/2019 Prowers Aggregate Operators, L... 12.75 1
04/04/2018 04/05/2018 Prowers Aggregate Operators, L... 12.25 1
10/05/2017 10/06/2017 Prowers Aggregate Operators, L... 8.50 1
09/20/2017 09/20/2017 Prowers Aggregate Operators, L... 10.50 1
04/18/2017 04/19/2017 Prowers Aggregate Operators, L... 26.75 1
12/05/2016 12/06/2016 Prowers Aggregate Operators, L... 5.50 1
10/27/2015 10/28/2015 Crossfire Aggregate Services,... 6.50 1
10/27/2015 10/27/2015 Crossfire Aggregate Services,... 0.25 1
06/09/2015 06/10/2015 Crossfire Aggregate Services,... 13.75 1
04/06/2015 04/07/2015 Crossfire Aggregate Services,... 12.50 1