Total: 29 inspections

Begin End Operator Hours Inspectors
01/13/2003 01/13/2003 Tennco Inc 18.00 2
06/26/2002 07/08/2002 Tennco Inc 2.50 1
05/13/2002 05/15/2002 Tennco Inc 20.00 1
04/24/2002 06/20/2002 Tennco Inc 97.50 2
03/26/2002 03/27/2002 Tennco Inc 11.50 1
03/21/2002 03/21/2002 Tennco Inc 4.00 1
03/15/2002 03/15/2002 Tennco Inc 16.00 2
03/12/2002 03/28/2002 Tennco Inc 78.50 2
03/05/2002 03/05/2002 Tennco Inc 8.00 1
03/05/2002 03/28/2002 Tennco Inc 55.00 2
02/27/2002 03/01/2002 Tennco Inc 18.00 1
02/21/2002 05/15/2002 Tennco Inc 18.00 1
02/19/2002 02/19/2002 Tennco Inc 10.00 1
02/11/2002 02/19/2002 Tennco Inc 22.00 1
02/07/2002 02/07/2002 Tennco Inc 6.00 1
02/07/2002 02/07/2002 Tennco Inc 6.00 1
02/05/2002 02/11/2002 Tennco Inc 5.00 1
01/09/2002 01/09/2002 Tennco Inc 8.00 1
12/26/2001 12/28/2001 Tennco Inc 19.00 1
12/19/2001 12/19/2001 Tennco Inc 9.00 1
12/17/2001 12/20/2001 Tennco Inc 32.00 1
12/12/2001 12/12/2001 Tennco Inc 4.00 1
11/06/2001 12/31/2001 Tennco Inc 95.00 2
10/04/2001 10/18/2001 Tennco Inc 50.00 1
10/02/2001 10/03/2001 Tennco Inc 18.00 1
09/26/2001 09/27/2001 Tennco Inc 18.00 1
09/10/2001 02/27/2002 Tennco Inc 10.00 1
08/13/2001 08/23/2001 Tennco Inc 29.50 2
08/09/2001 09/17/2001 Tennco Inc 57.50 1