Whitney Site — Inspections
Total: 24 inspections
| Begin | End | Operator | Hours | Inspectors |
|---|---|---|---|---|
| 08/17/2005 | 08/17/2005 | Reichard Contracting Inc | 4.50 | 1 |
| 08/03/2005 | 08/03/2005 | Reichard Contracting Inc | 4.50 | 1 |
| 03/22/2005 | 03/23/2005 | Reichard Contracting Inc | 15.00 | 1 |
| 05/25/2004 | 06/02/2004 | Reichard Contracting Inc | 5.25 | 1 |
| 05/25/2004 | 05/27/2004 | Reichard Contracting Inc | 5.25 | 1 |
| 05/21/2004 | 05/27/2004 | Reichard Contracting Inc | 11.25 | 1 |
| 04/29/2004 | 04/29/2004 | Reichard Contracting Inc | 1.50 | 1 |
| 09/05/2003 | 09/05/2003 | Reichard Contracting Inc | 2.00 | 1 |
| 08/06/2003 | 08/14/2003 | Reichard Contracting Inc | 3.25 | 1 |
| 07/29/2003 | 08/07/2003 | Reichard Contracting Inc | 16.75 | 1 |
| 06/24/2003 | 06/24/2003 | Reichard Contracting Inc | 3.50 | 1 |
| 05/20/2003 | 05/22/2003 | Reichard Contracting Inc | 36.50 | 2 |
| 04/22/2003 | 04/22/2003 | Reichard Contracting Inc | 4.75 | 1 |
| 02/19/2003 | 03/13/2003 | Reichard Contracting Inc | 18.00 | 1 |
| 01/16/2003 | 01/17/2003 | Reichard Contracting Inc | 6.00 | 1 |
| 12/04/2002 | 12/20/2002 | Reichard Contracting Inc | 6.00 | 1 |
| 12/04/2002 | 12/20/2002 | Reichard Contracting Inc | 7.00 | 1 |
| 10/09/2002 | 12/20/2002 | Reichard Contracting Inc | 22.25 | 2 |
| 09/05/2002 | 09/05/2002 | Reichard Contracting Inc | 5.25 | 1 |
| 06/27/2002 | 07/02/2002 | Reichard Contracting Inc | 6.50 | 1 |
| 06/27/2002 | 07/08/2002 | Reichard Contracting Inc | 5.75 | 1 |
| 06/25/2002 | 07/02/2002 | Reichard Contracting Inc | 21.75 | 1 |
| 05/07/2001 | 05/09/2001 | Reichard Contracting Inc | 2.50 | 1 |
| 03/20/2001 | 03/23/2001 | Reichard Contracting Inc | 4.75 | 2 |